Main Signaling Projects
2004 - 2021
2004
Operation of 3rd track on AYALON corridor, new interlocking,
increasing capacity from 6 to 10 trains/h
2006-2007
Operating 24 level crossings with Honeywell radar scanner
2008
Operation of first NTCC in Haifa
2010-2012
Deployment and taking into operation of short blocks on AYALON corridor, increasing capacity from 10 to 14 trains/h without additional track
2012-2014
Deployment and taking into operation new Marshalling Yard Operational System (Patent 258182, 30.07.2021)
2017-2023
Replacement of relay interlocking SpDrL-72 by electronic interlocking ESTW L90
2018-2023
ETCS L2: Main suppliers: Thales, Alstom, Bombardier, Siemens, Nokia, Motorola. The main goal: increasing capacity on AYALON corridor,
from 14 till 17 trains/h without additional track, today at final trial run stage
2020
Operation of new Main NTCC in Lod